Sign in Start free trial
Help centre › Modules

Visual Drawing (cladding assignment)

Assign the cladding pieces on a shop drawing to contractors by clicking on the drawing, and track how many square feet each one has.

What it is

Visual Drawing shows a building's cladding shop drawing on screen. Every panel (piece) on the drawing can be clicked. You select pieces and give them to a contractor. Each contractor gets their own colour on the drawing. The system adds up how many pieces and square feet each contractor has, and how much of the whole job is still not given out.

This module is made for cladding and facade work. It is switched on only for businesses whose package includes it.

Why you would use it

  • See at a glance who is doing which part of the building.
  • Pay and track contractors on true square footage, not guesses.
  • Make sure no panel is given out twice or forgotten.

How to use it

Drawings are imported for you by your system administrator. Once a drawing is in, it shows on the main page.

1. Open the list of drawings

  1. Click Visual Drawing in the left menu.
  2. Each drawing shows as a card with its number of pieces, its size in feet, and a progress bar of square feet assigned.

2. Set the square footage (Piece inventory)

Before you assign work, tell the system what each kind of piece measures.

  1. On the drawing's card, click Piece inventory.
  2. The table lists every shape on the drawing (diamond, rect or cut) with its Count.
  3. Rename a piece if the label is not what your team calls it.
  4. Enter Sq ft each. The grey hint shows what the drawing measures, as a guide.
  5. Click Save square footage. The Total sq ft for each shape and for the Whole drawing updates.

Leave a row blank and that shape counts as zero until you fill it in.

3. Assign work

  1. Click Assign work on the drawing's card, or Go to assignment from the piece inventory.
  2. Select pieces on the drawing:
    • Click a piece to select it.
    • Drag a box around many pieces to select them all.
    • Hold Shift while you drag to remove pieces from the selection.
  3. Use the zoom buttons, Fit, or your mouse wheel to zoom. Switch to the move tool to drag the drawing around.
  4. The status bar shows how many pieces and square feet are selected.
  5. Under Assign selection, choose the Contractor and click Save … pieces. The pieces turn that contractor's colour.
  6. To take pieces back, select them and click Unassign. Clear selection removes the selection without changing anything.

4. Track progress

The Progress box shows the percentage assigned, the square feet assigned out of the total, and how much is left. Below it, the contractor totals list each contractor with their colour, number of pieces and square feet.

Tips / common questions

  • Contractors come from your supplier contacts. Add the contractor as a supplier first.
  • Giving a piece that already belongs to someone to a new contractor moves it. Totals are counted again each time, so they always match the drawing.
  • A yellow warning on the assign page means some shapes have no square footage yet. Fix it in Piece inventory.
  • Two permissions control this module: one to view drawings and progress, and one to assign pieces and set square footage. Give them under Roles and permissions.